ATC TEMPLATE 04 DECISION PAPER


ATC TEMPLATE 04 DECISION PAPER

Question to answer: Should we do this?

(This is a stand-alone document that summarises the Project Idea, Business Case and Project Initiation Document (PID).)

WHAT IS THE CHANGE

Project Name:
Why should we prioritise this change?(This section is the executive summary which should provide concise details of the issue, the recommended action and expected benefits. Additional detail can be included in supporting documents.)
Situation
Recommended change
Benefits (i.e. the reasons that this merits a decision).
How much time and effort will this take?(This section should include detail key issues like time and resources - additional detail is needed this can be included in supporting documents.
How does this fit in with our strategy & our change programme?(How does this change fit into the bigger picture? Please draw a clear link between this change, the strategy and the change programme).


WHAT ARE THE IMPLICATIONS

What are the financial implications?(This section should detail costs v benefits and note the cash-flow implications. It may be co-authored by the Finance Team who will validate any necessary figures.)
Financial Cost
Financial Benefit
Net Impact
Source of funding
Cash flow implications
What are the implications for Governance, Audit, Compliance & Risk?(This section should refer to risks and where relevant refer to the risk noted in the risk log and the risk rating.)
What are the implications for our competitive position and reputation?(This section should refer to market impact/ customer impact, possibly regulatory or political risk.)
What are the implications for Ops, Health & Safety, Helpdesk & Facilities?(This section should refer to any changes to equipment, processes and procedures in store/care sites. If there will be an ongoing contractual arrangement with a supplier, this should be detailed here.)
What are the implications for HR, L&D and Training?(This section should detail any HR implications for recruitment, manpower, costs, roles & responsibilities, training etc.)
What are the implications for IT, Data & Info-Security?(This section should detail any IT implications on hardware, software, licensing, info-security, data etc. If there will be an ongoing service level agreement or support contract with a supplier, this should be detailed here.)


WHAT IS THE RECOMMENDATION

Recommendation / Action RequiredThis section should summarize the action or decision which is being sought.
This Decision Paper is asking the Exec Sponsor/Team to NOTE the following
This Decision Paper is asking the Exec Sponsor/Team to say YES to the following actions
Supporting PapersThis section should summarize any relevant supporting documents or past decisions.


WHAT IS THE DECISION
Actions Agreed / Notes from MeetingThis will be completed from the Minutes of each of the Meeting where discussed so as to provide a record of where the discussion is in process.


GUIDANCE

This is an explanation of the proposed Decision Paper Process
The following steps are proposed.

The template Decision Paper is completed by the author/sponsor. This is then circulated to key stakeholders for their review and approval to ensure that all the information is correct, any supporting papers are appended, and there is consensus on issues and recommendations before the Decision Paper is presented to the next Executive Team meeting.

The draft Decision Paper goes to the Strategy, Projects and Change Office to support and co-ordinate. This is to check that the Decision Paper is properly complete and circulated at least 5 days before the next Executive Team meeting, giving people the opportunity to read and think in advance. The Decision Paper may be classified as secure, confidential or secret and will be held according to that classification.

The Executive Team reviews the Decision Paper and will accept, reject or revise the paper (possibly asking for changes or further information). The Decision Paper and the outcome is then logged/filed with copies to the necessary people to effect agreed actions.

In some cases, following the Executive Team meeting the scale or seriousness of the decision may mean that the Decision Paper is then escalated for a Board decision. This follows a similar process to that described above and offers transparency on the step-by-step process from author > sponsor > Executive Team > Board

This is the proposed criteria for when a Decision Paper might be required:

IF
Less Than 5000Decision Paper not required
5000 - 25,000Decision required to be endorsed by Sponsor (line report executive only)
25,000 - 200,000Decision required to be endorsed by Sponsor and [Organisation Name] Exec
Above 200,000Decision required to be endorsed by Board


OR
If the Project/Proposal has a significant cross-functional impact on product, process or resources

OR
If the EMT decide there should be a Decision Paper

ATC TEMPLATE 03 PROJECT INITIATION DOCUMENT (FLIGHT PLAN)



ATC TEMPLATE 03 PROJECT INITIATION DOCUMENT (FLIGHT PLAN)
 
Question to answer: How will we do this?

At this step we need a written down detail of implementation plan: roles, goals, controls, tasks, owners, actions.

Process: Consult with the appropriate stakeholders, who will actually participate in the project. Write it all down on template and get agreement from your manager or Executive sponsor.
If you need any help please contact us in the Strategy, Projects and Change Office.

KEY INFORMATION
 
Project Title
Author
Sponsor
Current Date
SPCO Project Code


Why do we want to do this? How is it going to change the business?
(Basic background to the project explaining the situation, problem, need, context and priority. This essentially says why this needs to be done.)



WHAT IS THE PROJECT NOT GOING TO DELIVER?
 
(It is important to be clear about what is out of scope. What things are important, but not going to be delivered?)

WHO IS ON THE STEERING GROUP?
 
(List the key internal people who are not involved in the project but need to be informed of this document and the project (resources, time, budget, priority.)
PersonName & Role
Sponsor (who is ultimately accountable)
Key Supplier (who is delivering the change)
Key Customer (who will benefit from the change)


WHAT ARE THE ROLES OF THE PEOPLE DELIVERING THE CHANGE?
 
(List the key internal people and external people, their roles and responsibilities. Considering who is responsible, accountable, consulted or informed will help to identify the key stakeholder groups for the project.)

Name(s) & Job RolesWhich part(s) of the project? Person-days required
Responsible - The person who actually carries out the process or task. Gets the job done.


Accountable who is ultimately accountable for the job being done right. Responsible people are accountable to this person


Consulted people who are not directly involved with carrying out the task, but who are consulted. e.g. subject matter expert or advisor.


Informed Those who receive output from the process or task, or those who need to stay informed.




WHO WILL CHECK & APPROVE THE OUTPUTS OF THE PROJECT?
 
(List the key people who will review, approve & sign-off this document & the project (resources, time, budget, priority)
PersonRole








WHO WILL THE PROJECT OUTPUTS BE HANDED-OVER TO? WHEN?
 
(List the key people who will pick-up the outputs of this project when they are transitioned to Business As Usual)
PersonRoleAny training or support required?











THE PROJECT PLAN WHAT WERE GOING TO DO AND WHEN.
 
(List the key steps, phases, packages of work. This may be a table (as below), form, text, graphic or a Gantt Chart. What it needs to explain is how and when we will do each of the steps, phases and packages of work. It is a detailed summary of tasks, people, actions and dates.)
ItemDescription what is it & what does it do?Who is it for?Who is building/supplying it?How many days will this take?Cost Who is checking it & signing it off?Target DateStatusComments






















































































































































































RESOURCE PLAN WHAT SKILLS DO WE NEED & WHEN?
 
(What skills do we need and when do we need them? Understanding this will help us allocate people, or secure extra resources by contract, secondment, or other means.)

Internal People

Skill Set Needed e.g. PM, Analyst, Tester, BA etc.Name of person & current role (if internal)How many person-days do you need?When do you need them? (week/period/year)


































External People

Skill Set Needed e.g. PM, Analyst, Tester, BA etc.Name of person & current role (if internal)How many person-days do you need?When do you need them? (week/period/year)


































FUNDING PLAN HOW MUCH MONEY DO WE NEED & WHEN?
 
(What funding do we need and when do we need it? Understanding this will help us plan & allocate funds.)

Costs

Which elements of the project will cost How much do we expect to spend?When do we expect to spend it?When will we submit a CAPEX request?





























Total:



Income

Which elements of the project deliver the benefit/income?How much benefit / income do we expect?When is it expected to come in?When will we check the benefit has been received?





















Total:





Total Net Benefit:




RISKS WHAT DO WE NEED TO KEEP AN EYE ON?
 
(What could impact the success of the project? What unintended impacts could the project have?.)

RiskHow likely is it to happen (probability)What would the impact be?What could/should we do to limit this?Who should manage this risk?What is the risk rating in the register?












































DEPENDENCIES

What impacts this change?
What does this change impact?
How critical is this dependency? (from minor to game-changer)
e.g. data verification for member engagement?
Who owns the dependency?Do they know about this change?






















ATC TEMPLATE 02 PROJECT BUSINESS CASE

ATC TEMPLATE 02 PROJECT BUSINESS CASE

Question to answer: Is the cost/benefit worthwhile?

At this step we need a written down detail of strategic aim, cost, benefit in a format acceptable to finance for investment or project appraisal

Process: Get a CAPEX FORM  fill it in. Attach it to the Business Case template and get sign-off from your manager or exec (depending on the value)

If you need any help please contact the Strategy, Projects and Change Office

KEY INFORMATION

Project Title
Author
Sponsor
Current Date
SPCO Project Code


WHICH BU OR FUNCTION IS THIS FOR? WHICH PROGRAMME WILL THIS BE PART OF?

Name of Business Unit, Support Function or Corporate
Strategic Programme


Project Type (tick all that apply)CapitalPropertyITOther (specify)


PROJECT SUMMARY


What are the key benefits of this change?
(Highlight the key points, which should include important benefits and the return on investment (ROI))

How have your tested/trialed this idea?
(Please attach documentation showing any test/trial results or other supporting research)

What other options are available?
(Analysis and reasoned recommendation for the base business options of: do nothing, do the minimal or do something)



WHAT ARE THE TIMESCALES?

(The period over which the project will run (summary of the Project Plan) and the period over which the benefits will be realized. This information is subsequently used to help timing decisions when planning (Project Plan, Stage Plan and Benefits Review Plan)

YearProject Stages (1-7)Expected Benefits Realised


























WHAT ARE THE MAJOR RISKS?

(Give a summary of the key risks associated with the project together with the likely impact and plans should they occur)

RiskHow likely is it to happen (probability)What would the impact be?What could/should we do to limit this?Who should manage this risk?
































WHAT ARE THE BENEFITS, DISBENEFITS AND COSTS OF THIS CHANGE?

(The benefits that the project will deliver expressed in measurable terms against the situation as it exists prior to the project. Benefits should be both qualitative and quantitative. They should be aligned to programme benefits.

Dis-benefits are actual consequences of an activity (unlike a risk, which is uncertain). E.g. merging two elements of an organization onto a new site may lead to better joint working and lower costs but lead to dis-benefits (e.g. drop in productivity during the merger). Dis-benefits need to be valued and incorporated into the investment appraisal)

Benefits / DisbenefitsValue






Total
Project / One-off CostsValue






Total


Ongoing / Annual Costs






Total


INVESTMENT APPRAISAL SUMMARY

(The analysis may use techniques such as cash flow statement, ROI, net present value, internal rate of return and payback period. The objective is to be able to define the value of a project as an investment. The investment appraisal should address how the project will be funded)

HeadingTargetLow/LowMedium/MediumHigh/High
Accounting Rate of ReturnDoes the project meet the target return?12


Payback Period (Years) How long will it take to repay the initial investment?67
of Life
or 10 years



Interest Cover Multiple2




ATC TEMPLATE 01 PROJECT IDEA SUMMARY (PROJECT BRIEF)




ATC TEMPLATE 01 PROJECT IDEA SUMMARY (PROJECT BRIEF)

Question to answer: Is this a good idea?

At the idea stage we need a written down explanation in a simple form (possibly supported with a market analysis and supplier documentation) outlining strategic aim, cost, benefit for initial evaluation. This allows the team to understand what the project is/is not and whether we want to proceed to a business case.

Please add additional rows to any of the sections as necessary. Only provide summarized information but attach detailed analysis as an appendix if needed.
If you need any help please contact the Strategy, Projects and Change Office (SPCO)

KEY INFORMATION

Project Title
Author
Sponsor
Current Date


WHICH BUSINESS UNIT, FUNCTIONAL OR CORPORATE STRATEGY DOES THIS SUPPORT?

Name of Business Unit, Support Function or Corporate
Strategic Programme


Project Type (tick all that apply)CapitalPropertyITOther (specify)


PROJECT SUMMARY

What is this change?
(The description should be a clear but brief description of the project. Summarize the size/scale, complexity and expected timescale of this change. In ATC terms, is this a jumbo jet, an aircraft carrier or a small propeller plane?) e.g. This is a full replacement of our central product and price management IT systems

Why do we want to do this? How is it going to change the business?
(Think in terms of what is this project doing to meet the aims and objectives of CICS Why are we doing this? What will the business be able to do after this change, that it cant do now?)

What are the key things that we will deliver?
(What are the things that will be delivered/complete as part of this? Think of this like a shopping list of tasks or items that need to be completed and that can be allocated to people to deliver. Ideally give an estimate of the time and cost.)


ItemDescription what does it do?Who is it for?Who is making/ supplying it?How long could it take?What is it likely to cost?






































WHAT SKILLS ARE WE LIKELY TO NEED AND WHEN?

(Think about this in person days - identifying if the skills are internal from business unit(s), internal from support function(s) or from external suppliers or consultants. You will be asked for more detail in the Project Initiation Document).

RolePerson-days










WHAT DO WE EXPECT THE FINANCIAL COST/BENEFIT TO LOOK LIKE?

(What financial benefit do we expect? You will be asked for more detail in the Business Case).


Year 1Year 2Year 3Ongoing
Expected Costs



Expected Benefits



Net Benefit/Cost





WHAT ARE THE TOP THREE RISKS AND DEPENDENCIES THAT WE ARE AWARE OF NOW?

(What should the decision-makers consider when looking at this project?).
Risks what are we uncertain about?Dependencies what does this impact / impacts on this?








AUTHORITY TO PROCEED

Signed By:Role in ProjectDate








ATC MATURITY MATRIX

ATC MATURITY MATRIX

INTRODUCTION

In this simple guide to project management I will use the analogy of the Project Management Office being like Air Traffic Control for projects and change. The Project Management Office [PMO] will want confidence that any significant project or change is clear about passengers and crew (participants), fuel (budget), destination (outcome) and route (plans). For each initiative we want to be able to give it a thumbs-up or guidance on what is required for permission to take-off or indeed a safe journey: on-time, on-budget, to-specification, low-risk and high-communication.

This simple guide is based on a blend of Waterfall approach (plan before action eg PRINCE2) and Agile (work it out as you do eg SCRUM)

ATC MATURITY MATRIX


Level1Level2Level3
Management ControlProject management terminology is used by some members of the organization but not consistently and possibly not understood by all stakeholders. Projects will be conducted and managed according to individual preferences.The concepts of project management will have been grasped by the organization, and there may be local experts, such as experienced project managers, working on key projects.There is a centrally defined and documented approach to a project management life cycle and controls, and it is applied in all projects by capable staff who support project teams.
Benefits ManagementThere is some recognition that the concept of benefits can be differentiated from project outputs.Benefits are recognized as an element within project business cases. There may be some documentation regarding who is responsible for particular benefits and their realization, but this is unlikely to be followed through or consistent.There is a centrally managed and consistent framework for defining and tracking the realization of benefits from project outputs.
Financial ManagementThere is little or no financial control at project level. There is a lack of accountability and monitoring of project expenditure.Project business cases are produced in various forms and the better and more formal cases will present the rationale on which to obtain organizational commitment to the project. Overall cost of the project is not monitored or fully accounted for.There are centrally established standards for the preparation of business cases and processes for their management throughout the project life cycle. Project managers monitor costs and expenditure in accordance with organizational guidelines and procedures, with defined interfaces with other financial functions within the organization.
Stakeholder EngagementStakeholder engagement and communication is rarelyused by projects as an element of the delivery toolkit.Projects will be communicated to stakeholders, but this is linked more to the personal initiative of projectmanagers than to a structured approach being deployed by the organization.There is a centrally managed and consistent approach to stakeholder engagement and communications used by all projects.
Risk ManagementThere is minimal evidence of risk management being used to any beneficial effect on projects. There may be evidence of risks being documented but little evidence of active management.Risk management is recognized and used on projects, but there are inconsistent approaches, which result in different levels of commitment and effectiveness.Project risk management is based on a centrally defined process that is cognizant of the organizations policy for the management of risks and is used consistently.
Organisational GovernanceSome informal governance of projects exists but has undefined links to broader organizational controls. Roles are unlikely to be formally defined.Project management from an organizational perspective is beginning to take shape but with ad hoc controls and no clear strategic control. Roles and responsibilities will be inconsistent, as will reporting lines.Centrally defined organizational controls are applied consistently to all projects, with decision-making structures in place and linked to organizational governance.
Resource ManagementThere is some recognition within the organization of the need to manage resources effectively to enable successful delivery of projects, but little evidence of resource acquisition, planning or management.Resources are being deployed across the organization and individual projects have an approach to resource acquisition, planning or management. However, there is little evidence of consistency of approach.The organization has a centrally defined and adopted set of procedures and management processes for acquiring, planning and managing project resources.


USEFUL LINKS AND REFERENCES

About Agile
https://www.guru99.com/waterfall-vs-agile.html

About Waterfall and the leading approach to Waterfall which is PRINCE2
https://prince2.wiki/

ABOUT THE BLOG

This is a series of coaching blogs that eventually will become a book. By blogging each item I hope to share each element in easy to read bite size chunks, maybe invite some people to subscribe to see the next posting and hopefully encourage some comments, feedback and suggestions which will improve the content for the blog and eventually the book. All comments and feedback are therefore welcome.


ATC MANAGING RISKS AND ISSUES

ATC MANAGING RISKS AND ISSUES

INTRODUCTION

In this simple guide to project management I will use the analogy of the Project Management Office being like Air Traffic Control for projects and change. The Project Management Office [PMO] will want confidence that any significant project or change is clear about passengers and crew (participants), fuel (budget), destination (outcome) and route (plans). For each initiative we want to be able to give it a thumbs-up or guidance on what is required for permission to take-off or indeed a safe journey: on-time, on-budget, to-specification, low-risk and high-communication.

This simple guide is based on a blend of Waterfall approach (plan before action eg PRINCE2) and Agile (work it out as you do eg SCRUM)

ATC MANAGING RISKS AND ISSUES

Risk management responses can be a mix of five main actions transfer, tolerate, treat, terminate or take the opportunity. Transfer for some risks, the best response may be to transfer them. need to be set and should inform your decisions. Treat by far the greater number of risks will belong to this category.

Risk IDRisk DescriptionProbabilityImpactScoreOwnerAction TakenNote
ID No001A short description 133InitialsTolerateA short description
ID No002A short description 236InitialsTransferA short description
ID No003A short description 339InitialsTreatA short description
ID No004A short description 4312InitialsTerminateA short description
ID No005A short description 5315InitialsTakeA short description
ID No006A short description 3515InitialsTolerateA short description
ID No007A short description 3412InitialsTransferA short description
ID No008A short description 339InitialsTreatA short description
ID No009A short description 326InitialsTerminateA short description
ID No010A short description 313InitialsTakeA short description
ID No011A short description 313InitialsTolerateA short description


ABOUT THE BLOG

This is a series of coaching blogs that eventually will become a book. By blogging each item I hope to share each element in easy to read bite size chunks, maybe invite some people to subscribe to see the next posting and hopefully encourage some comments, feedback and suggestions which will improve the content for the blog and eventually the book. All comments and feedback are therefore welcome.


ATC MANAGING PEOPLES TASKS AND WORKLOAD

ATC MANAGING PEOPLES TASKS AND WORKLOAD

INTRODUCTION

In this simple guide to project management I will use the analogy of the Project Management Office being like Air Traffic Control for projects and change. The Project Management Office [PMO] will want confidence that any significant project or change is clear about passengers and crew (participants), fuel (budget), destination (outcome) and route (plans). For each initiative we want to be able to give it a thumbs-up or guidance on what is required for permission to take-off or indeed a safe journey: on-time, on-budget, to-specification, low-risk and high-communication.

This simple guide is based on a blend of Waterfall approach (plan before action eg PRINCE2) and Agile (work it out as you do eg SCRUM)

PLANNING PEOPLES TASKS AND WORKLOAD

Resource planning: who does what, when, is really important. This is essential to be able to manage communication, co-ordination and collaboration

WhoWhatPeriod1Period2Period3Period4Total
Name001Tasks21205
Name002Tasks11204
Name003Tasks10203
Name004Tasks11204
Name005Tasks11237
Name006Tasks11035
Name007Tasks00134
Name008Tasks00235
TOTALS
75131237


ROLES FOR DECISIONS AND COMMUNICATION

It is useful to think of all the people who need to be involved in communication, co-ordination and collaboration

Responsible: person who performs an activity or does the work.
Accountable: person who is ultimately accountable and has Yes/No/Veto.
Consulted: person that needs to feedback and contribute to the activity.
Informed: person that needs to know of the decision or action.

A COMMUNICATION PLAN

What is saidWho says itWhen it is saidWhat method/medium is used
List of optionsList of optionsList of optionsList of options
Explanation of aimThe sponsorBefore the startEmail
Explanation of approachThe project managerAt the startMeeting
Explanation of budgetThe team leaderDuring the projectLetter
Explanation of benefitThe customerAt completionBriefing
Explanation of scheduleThe ownerWhen finishedPresentation
Add moreAdd moreAdd moreAdd more
Add moreAdd moreAdd moreAdd more
Add moreAdd moreAdd moreAdd more


A COMMUNICATION CALENDAR

Period 1Period 2Period 3Period 4Period 5Period 6
Newsletter No1Newsletter No2Newsletter No3Newsletter No4Newsletter No5Newsletter No6
Briefing No1Briefing No2Briefing No3Briefing No4Briefing No5Briefing No6
Meeting No1Meeting No2Meeting No3Meeting No4Meeting No5Meeting No6
Report No1Report No2Report No3Report No4Report No5Report No6


ABOUT THE BLOG

This is a series of coaching blogs that eventually will become a book. By blogging each item I hope to share each element in easy to read bite size chunks, maybe invite some people to subscribe to see the next posting and hopefully encourage some comments, feedback and suggestions which will improve the content for the blog and eventually the book. All comments and feedback are therefore welcome.